Re: Re-order point

$
0
0

hi

 

yes Reoder point can be linked to scheduling agreement.

 

For understanding you can use below example:

 

1 .You need to have a scheduling agreement created for the material and vendor combination

2.  In material master , you need to maintain manual reorder point "VB" say value - 500 with lot size say 1000.

3. sourcelist needs to be updated with scheduling agreement  = outline agreement with item number, Porg and vendor and also with usage  "2 -Record relevant to MRP. Sched. lines generated automatically".

4. addtital check in material master , procurement type F

 

Result: Schedule line will get generated automatically for Scheduling agreement for 1000

 

You can further use Quota arrangment if required.